Data Centre Server & Networking Equipment

Sale Type:

Private Treaty

Offers Due:

20 May 2021, 12pm BST

Location:

Normanton, North Yorkshire

Server and Networking Equipment at the Arcadia Data Centre, Normanton

By Order of Matthew David Smith, Daniel Francis Butters and Robert Scott Fishman, all of Deloitte LLP, Joint Administrators of Arcadia Group Limited (“AGL” / “the Company”)

All items are subject to availability

  • Cisco Prime UCS C220 M4 Rack Server with 4x N20-BBLKD HDD Blanking Panels and 4x 900GB SAS Hard Drives
  • Cisco 3495 Secure Network Server with 6x N20-BBLKD HDD Blanking Panels and 2x 600GB SAS Hard Drives
  • Cisco Secure Infrastructure with 6x N20-BBLKD HDD Blanking Panels and 2x 600GB SAS Hard Drives
  • Catalyst C6807-XL Core Units comprising of;  Cisco WS-X6848-SFP, Cisco WS-X6848-GE-TX, Cisco VS-SUP2T-10G, Cisco WS-X6848-GE-TX, Cisco WS-X6904-40G and Cisco C6807-XL
  • Dell PowerEdge M1000e Blade Center with 15x M620 Blades Each with 2x 300GB SAS Drives
  • Dell PowerEdge M1000E with 15x M620 Blades Complete with 2x 300GB SAS Hard Drives
  • (2) IBM System x3750 M4 4 Socket Servers Each with 7x 300GB SAS Hard Drives
  • IBM BladeCenter H Server with 7 HX5 Blades and 12x IBM EXP M2524 each with 24x 600GB SAS Drives
  • Several Dell PowerEdge VRTX Chassis’ Complete with Blades and SAS Hard Drives
  • Dell PowerEdge R730XD Rack Mount Server with 14x 800GB SSD Drives
  • Dell PowerEdge R720 Rack Mount Server with 8x 300GB SAS Hard Drives
  • Dell DR4100 with 12x 1TB SAS Hard Drives
  • Cisco Switchgear, Paloalto Firewall Appliances, Kemp Technologies Load Balancer, Server Lift SL350X and More

Removal

  • Removal Deadline: TBC May 2021, 4:30pm BST Strictly by prior appointment only
  • Removal Hours: TBC May 2021, 9:30am – 4:30pm BST, Strictly by prior appointment, excluding weekends
  • Collection is only permitted once a paid in full invoice has been received
  • The Buyer and or their removal contractor must supply their own lifting equipment Method statements and risk assessments, copies of all relevant insurances documents and operator licenses must be supplied and approved ahead of any item being dismantled or moved in accordance with Health & Safety policies. Site attendance for the duration of the removal process to be confirmed and agreed in advance
  • Anyone attending site will be required to wear the relevant PPE workwear including Hi-Viz Vest/Jacket and Safety Footwear. In accordance with Government Covid-19 Guidelines all visitors to site must wear PPE including gloves & face coverings. If visitors don’t have gloves or face coverings these will be supplied. Visitors must inform the site manager if they are ill or have been ill prior to visiting site. Social distancing measures will be in place and hand sanitising facilities will be available

Terms & Conditions

  • Buyer’s Premium of 15% will be applicable to this sale
  • VAT at 20% will be added to the total price and Buyer`s Premium (There may be exceptions)
  • Credit cards are NOT accepted as payment against your invoice. All payments are to be made via bank transfer – account details will be shown on your invoice.
  • All payments must be cleared in our account by Friday 21 May 2021, 3:00pm BST, Strictly by prior appointment
  • All persons arriving on site must report to the entrance and complete the signing in procedure book
  • This site is a full PPE area and everyone must comply whilst the site is designated as such. PPE worn must comply with all relevant Method Statements. Anyone not found wearing his/her PPE will be required to leave the site, if in doubt assistance must be sought from the site Supervisor
  • Covid restrictions may apply
  • View Standard Terms & Conditions.

Contacts

Kevin Smyth
Assoc. RICS

Managing Director

London Office

+44 (0) 7920 149064

ksmyth@hilcoglobaladvisors.co.uk